ELECTRICITY
How to Generate Mega- Problems
Power plants intended for the 10,000 MW project cannot start operation because parts from China are broken. BPK finds that PLN does not manage the project according to regulations.
November 16, 2011
FOR the past two weeks the turbine at Lontar Steam Power Plant (PLTU) Unit I in Tangerang regency, Banten, has been idle. The last performance test prior to commercial operations of the power plant built by PT PLN, the consortium of Dongfang Electric Corporation, China and PT Dalle Energy, that should have been done at the end of last month was cancelled.
Project Manager Herry Nugraha explained that the Unit was still idle because the traveling
...