Chasing Targets

November 6, 2017

The government is accelerating construction on various infrastructure projects around the country. Some nearly reached the target set in the National Mid-Term Development Plan (RPJMN) of 2015-2019. However, quite a few are still far from their finish lines.

Roads

New Roads
2015-2019 RPJMN Target: 2,650 km
Completed as of September 2017: 2,623 km
Not yet completed: 27 km

New Toll Roads
2015-2019 RPJMN Target: 1,851 km
Completed as of September 2017: 23




...