Burnt by Coal
Coal price increases are driving PLN up the wall. Subsidies may soar to Rp90 trillion.
July 8, 2008
THE tender for the supply of coal to power plant Tanjung Jati B in Central Java, had to be repeated. It was not due to lack of participants or incomplete tender participant requirements. The cause was the project owner, PLN, the State Electricity Company. “All participants proposed prices far above the Indonesia Coal Index which PLN uses as a guideline,” said Deputy CEO of PLN, Rudiantara.
PLN set a purchasing price of US$80 per ton. However
...