Piling Projects at Cikampek
Inconsistent progress of three projects at the Jakarta-Cikampek toll road caused restlessness among sub-contractors supplying heavy equipment.
Putri Adityowati
December 4, 2018
The project work is now being rearranged not long after an announcement for temporary suspension.
A number of heavy equipment provider subcontractors repeatedly contacted Adhi Karya’s general manager for light rail transit (LRT), Isman Widodo, on Tuesday two weeks ago. They asked about the LRT project from Cawang to East Bekasi, which spans 18.5 kilometers. The day before, Transportation Minister Budi Karya Sumadi requested the LRT
...