Goodbye Masela

The development of the Masela Block could be uncertain once more after Shell announced its intention to withdraw. This is the result of constantly changing government policies.

Tempo

July 27, 2020

THERE is now a heavy price that must be paid for the decision by the government to change the Masela Block development scheme. As a result of forcing the liquified natural gas (LNG) processing facility to be built on land, the megaproject is now far behind schedule. It is now threatened with coming to a halt completely after Shell Upstream Overseas Services Ltd announced its intention to withdraw from Masela.