How to Generate Mega- Problems

Wednesday, November 16, 2011

Power plants intended for the 10,000 MW project cannot start operation because parts from China are broken. BPK finds that PLN does not manage the project according to regulations.

arsip tempo : 178034310784.

. tempo : 178034310784.

FOR the past two weeks the turbine at Lontar Steam Power Plant (PLTU) Unit I in Tangerang regency, Banten, has been idle. The last performance test prior to commercial operations of the power plant built by PT PLN, the consortium of Dongfang Electric Corporation, China and PT Dalle Energy, that should have been done at the end of last month was cancelled.

Project Manager Herry Nugraha explained that the Unit was still idle because the traveling

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 750.000/12 months

  • *Flexible payment methods
  • *Unlimited access to Tempo Plus & Tempo Magz

Rp 386.280/6 months

  • *Auto-renews every 6 months
  • *Cancel at anytime
  • *Unlimited access to Tempo Plus & Tempo Magz

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • June 1, 2026

  • May 25, 2026

  • May 18, 2026

  • May 11, 2026

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe