How to Generate Mega- Problems

Wednesday, November 16, 2011

Power plants intended for the 10,000 MW project cannot start operation because parts from China are broken. BPK finds that PLN does not manage the project according to regulations.

arsip tempo : 173237730134.

. tempo : 173237730134.

FOR the past two weeks the turbine at Lontar Steam Power Plant (PLTU) Unit I in Tangerang regency, Banten, has been idle. The last performance test prior to commercial operations of the power plant built by PT PLN, the consortium of Dongfang Electric Corporation, China and PT Dalle Energy, that should have been done at the end of last month was cancelled.

Project Manager Herry Nugraha explained that the Unit was still idle because the traveling

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 54.945/Month

Active for 12 Months, Rp 659.340

  • *You Save -Rp 102.000
  • *Guaranteed update of up to 52 Editions of Tempo Magazine

Rp 64.380/Month

Active Every Month Cancel Anytime

  • *Free for the first month if using a Credit Card

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • November 18, 2024

  • November 11, 2024

  • November 4, 2024

  • October 28, 2024

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe