maaf email atau password anda salah

Oil
Emission Impossible

Tuesday, August 25, 2009

Production is again delayed from Cepu as the government presses Mobil, operator of the block, to make good its promise to start producing at the earliest date.

arsip tempo : 173496954855.

. tempo : 173496954855.

THE flames licked at the sky from piping at Well A of the Banyu Urip Field in the East Java district of Bojonegoro on August 17 as Mobil Cepu Limited (MCL), operator of the oil block, disposed of produced gas by burning it in the atmosphere.

For the past few weeks, MCL had worked overtime to test the well before putting it on-stream. “The signs are good,” said Field External Relations Manager, Deddy Afidick. “The flames spewing from the pi

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 54.945/Month

Active for 12 Months, Rp 659.340

  • *You Save -Rp 102.000
  • *Guaranteed update of up to 52 Editions of Tempo Magazine

Rp 64.380/Month

Active Every Month Cancel Anytime

  • *Free for the first month if using a Credit Card

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • December 23, 2024

  • December 16, 2024

  • December 9, 2024

  • December 2, 2024

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe