Oil
Emission Impossible

Tuesday, August 25, 2009

Production is again delayed from Cepu as the government presses Mobil, operator of the block, to make good its promise to start producing at the earliest date.

arsip tempo : 178037299729.

. tempo : 178037299729.

THE flames licked at the sky from piping at Well A of the Banyu Urip Field in the East Java district of Bojonegoro on August 17 as Mobil Cepu Limited (MCL), operator of the oil block, disposed of produced gas by burning it in the atmosphere.

For the past few weeks, MCL had worked overtime to test the well before putting it on-stream. “The signs are good,” said Field External Relations Manager, Deddy Afidick. “The flames spewing from the pi

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 750.000/12 months

  • *Flexible payment methods
  • *Unlimited access to Tempo Plus & Tempo Magz

Rp 386.280/6 months

  • *Auto-renews every 6 months
  • *Cancel at anytime
  • *Unlimited access to Tempo Plus & Tempo Magz

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • June 1, 2026

  • May 25, 2026

  • May 18, 2026

  • May 11, 2026

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe