Construction in the Slow Lane

Wednesday, September 8, 2010

The government is to review 24 toll road concessions on Java. Why has the Jakarta-Surabaya toll road mega-project not yet materialized?

arsip tempo : 173033067065.

. tempo : 173033067065.

THE red-painted steel poles were in rows on the 11-kilometer stretch of land. This is the road that will later be filled with cars, especially when people go home at Lebaran. Leading to nine districts, the arrival of the Batang-Semarang, Central Java toll road, has long been awaited.

However, when Tempo visited on Wednesday last week, there was no land being measured, let alone any road works. In fact Heru Prasetyo, head of the land supply team,

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 54.945/Month

Active for 12 Months, Rp 659.340

  • *You Save -Rp 102.000
  • *Guaranteed update of up to 52 Editions of Tempo Magazine

Rp 64.380/Month

Active Every Month Cancel Anytime

  • *Free for the first month if using a Credit Card

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • October 28, 2024

  • October 21, 2024

  • October 14, 2024

  • October 7, 2024

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe