Suspended Ambition

Wednesday, January 19, 2011

Second-phase 10,000-megawatt power generators mostly utilize geothermal energy. Regional hindrance is in their way.

arsip tempo : 178036958937.

. tempo : 178036958937.

THE government’s ambition to see its second-phase 10,000 MW power generator development project operational in 2014 apparently has to be restrained. Geothermal mining concession holders winning tenders have not yet started their exploration activities yet so far. Only the state oil/gas company PT Pertamina has explored this renewable source of energy.

The slow completion of the geothermal project is due to three things. Land licensing is as ye

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 750.000/12 months

  • *Flexible payment methods
  • *Unlimited access to Tempo Plus & Tempo Magz

Rp 386.280/6 months

  • *Auto-renews every 6 months
  • *Cancel at anytime
  • *Unlimited access to Tempo Plus & Tempo Magz

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

  • Letters

    Tempo English Wednesday, January 19, 2011

  • Letters

    Tempo English Wednesday, January 19, 2011

  • Letters

    Tempo English Wednesday, January 19, 2011

  • Letters

    Tempo English Wednesday, January 19, 2011

More exclusive contents

  • June 1, 2026

  • May 25, 2026

  • May 18, 2026

  • May 11, 2026

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe