maaf email atau password anda salah

The Dream of "West Coast" Tourism

Tuesday, November 5, 2013

In some areas, the MP3EI project has been delayed by infrastructure problems and land disputes. Many projects will not be completed on time.

arsip tempo : 173228076260.

. tempo : 173228076260.

There was a noticeable lack of activity around the coal-fired steam power plant (PLTU) about 40 kilometers from Ambon, capital of Maluku in eastern Indoneisa. There were only three security guards on duty when Tempo visited in mid-July, and they were just sitting around. About 100 meters from the security post there was some steel framework, partially painted blue.

"There is no activity," said one security guard for PT Hilmanindo Signintama. "All

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 54.945/Month

Active for 12 Months, Rp 659.340

  • *You Save -Rp 102.000
  • *Guaranteed update of up to 52 Editions of Tempo Magazine

Rp 64.380/Month

Active Every Month Cancel Anytime

  • *Free for the first month if using a Credit Card

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • November 18, 2024

  • November 11, 2024

  • November 4, 2024

  • October 28, 2024

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe