Jawa-1 PLTGU Financial and Technical Problems

Operators of the Jawa-1 steam-gas power plant are in a financial strain. Technical problems are slowing down the project’s development.

Retno Sulistyowati

February 19, 2024

THE deadline to operate the Jawa-1 steam-gas power plant or PLTGU in Cilamaya, Karawang Regency, West Java, was over two years ago. But as of mid-February, only the unit 2 generator with an 880 megawatt (MW) capacity has been operating commercially. The unit 1 generator, scheduled to start running in January, failed to meet the deadline.

Norman Ginting, Project and Operations Director of Pertamina Power Indonesia (PPI), said that one unit of the

...