Contractors Crushed by Soaring Prices

Monday, September 26, 2022

Contractors of infrastructure projects demand cost and contract adjustments as material prices escalate. There are risks, from a drop in quality to stalled projects.

arsip tempo : 176913453913.

A worker carries out a finishing work on the construction of the Cibitung-Cilincing Toll Road (JTCC) section 4 in Marunda, North Jakarta, July 19. ANTARA/M. Risyal Hidayat . tempo : 176913453913.

BASUKI Muchlis’ invitation for an online meeting on Tuesday, September 20, had an important agenda. Basuki, Executive Director of the Indonesian Contractors Association (AKI), invited AKI’s members to gather data and set up equations for their current contracts and infrastructure projects.

The meeting took place two days after the invitation was sent. Basuki told Tempo that if the construction contracts are not adjusted, those contra

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 750.000/12 months

  • *Flexible payment methods
  • *Unlimited access to Tempo Plus & Tempo Magz

Rp 386.280/6 months

  • *Auto-renews every 6 months
  • *Cancel at anytime
  • *Unlimited access to Tempo Plus & Tempo Magz

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • January 19, 2026

  • January 12, 2026

  • January 5, 2026

  • December 29, 2025

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe