The Pool Strategy to Stop Flooding in Jakarta

Monday, December 20, 2021

Jakarta’s perennial flooding problem will be controlled using a system of massive water containment. Infiltration wells are deemed unsuitable for the soil characteristics of the city.

 

arsip tempo : 171410915623.

The construction site of the Ciawi and Sukamahi Dams in Ciawi, Bogor Regency, West Java, Friday, September 3, 2021. TEMPO/M Taufan Rengganis. tempo : 171410915623.

ORIGINALLY planned to be completed by the end of this year, the dry dam construction in Sukamahi Village, Megamendung District, Bogor Regency, West Java, is currently still ongoing. The resevoir, meant to mitigate Jakarta’s perennial flooding problems, has been under construction since December 2, 2016. “The Sukamahi Dam construction is now focused on embankment work, with progress at 98.30 percent,” said the Director of Da

...

Subscribe to continue reading.
We craft news with stories.

For the benefits of subscribing to Digital Tempo, See More

The Best Choice

Rp 54.945/Month

Active for 12 Months, Rp 659.340

  • *You Save -Rp 102.000
  • *Guaranteed update of up to 52 Editions of Tempo Magazine

Rp 64.380/Month

Active Every Month Cancel Anytime

  • *Free for the first month if using a Credit Card

See Other Packages

Already a Subscribed? Log in here
To receive daily news by Email, Sign up for Tempo ID.

More Articles

More exclusive contents

  • April 22, 2024

  • April 15, 2024

  • April 4, 2024

  • April 1, 2024

Independent journalism needs public support. By subscribing to Tempo, you will contribute to our ongoing efforts to produce accurate, in-depth and reliable information. We believe that you and everyone else can make all the right decisions if you receive correct and complete information. For this reason, since its establishment on March 6, 1971, Tempo has been and will always be committed to hard-hitting investigative journalism. For the public and the Republic.

Login Subscribe